Sewer plant press may be ready before anyone can install it
The new sludge press for the plant East Hampton shares with Colchester could be ready to ship in January or February. The job of installing it cannot be advertised until the state approves the plans.
The sewer plant East Hampton shares with Colchester may have to pay for a new machine and then put it in storage. Its new belt filter press, which squeezes water out of sludge, could be ready to ship in January or February, and the job of installing it cannot be advertised until the state approves the plans.
If no contractor is in place to receive the press, the manufacturer will be due payment and the press will go into storage, the plant's engineering firm, Tighe & Bond, wrote on Oct. 22. The Colchester-East Hampton Joint Facilities Committee, the two towns' joint committee for the plant, voted 5-0 on Oct. 26 to approve up to $23,500 for more design work on the press by Tighe & Bond.
The state Department of Energy and Environmental Protection plans to review the plans and specifications, and the project cannot be advertised until the department approves them, the firm wrote. It said it is uncertain how long the review will take, but it hoped the review would be short, because the project is paid for locally and Tighe & Bond will certify that it meets the state's guidelines.
Because of what the committee's minutes call "urgent project timelines," Stephen Seigal, the firm's project director, recommended asking the state to let the plant advertise for an installer while the review is under way.
The extra design work comes from the sludge holding tank in the plant's service building, which raised issues in the firm's structural and code reviews that its original task order did not cover, the letter says. Tighe & Bond will design a monorail hoist to move totes of polymer, a chemical, into containment, and ventilation for the tank to reduce the chance of combustible and corrosive gases building up, along with a combustible gas detector. The floor needs four beams for support, the minutes say. The work also covers designing changes to an equipment room to improve the exit path near the new press, after a meeting with the building official. Most of the money, $14,400, is for structural engineering and drafting.
A superintendent without the water work
The superintendent's job description is to be rewritten to drop the requirements for state Class I water and Class I water distribution licenses and to strike all language about supporting the operation and maintenance of East Hampton's public water system, the committee's minutes say. The balance of labor requirements between Colchester and East Hampton "requires review and resolution," they say.
The town's posting for the job, dated Sept. 21, listed both water licenses and said the superintendent would support the water system as needed. It offered a starting salary of $106,000 to $125,000 and closed Oct. 19 or when the job is filled. The job was open in October, and Bruce Gudelski is the plant's interim superintendent, the minutes say.
The firm Inframark has been retained to help with water sampling for the plant's wastewater facilities plan, and short-term operating help will be available while the plant hires, the minutes say.
East Hampton's Water Pollution Control Authority, for now the Town Council sitting as the town's sewer board, had both the press and the job description on its Nov. 3 agenda. The town had not posted minutes from that meeting as of Saturday.