Sewer rates, the pump stations, and the council sitting as the sewer authority.

The story so far

The Town Council has been sitting as the Water Pollution Control Authority, the board that sets sewer rates, in an arrangement one member said was meant to last about six months.

On Sept. 1 it held the sewer rate at $605 per unit and raised the grinder pump fee from $500 to $600. Bills go out Sept. 29 and are due Oct. 1.

In September the council began discussing an ordinance that would hand day-to-day operations to a separate Water and Sewer Commission.

East Hampton sewer ordinance: public hearing Nov. 24

A new board of seven residents would run East Hampton's sewers and set the rate on your bill. Residents can speak at a hearing Nov. 24.

A board of seven East Hampton residents, appointed by the Town Council, would run the town's sewers and set the sewer rate on your bill under an ordinance the council sent to a public hearing Tuesday night. Residents can speak on it at the hearing, set for the council's meeting on Tuesday, Nov. 24, at 6:30 p.m. in the Town Hall Council Chambers.

For now the seven council members are themselves the town's Water Pollution Control Authority (WPCA), the body state law puts in charge of a town's sewers and the one that sets the rate (more on that). The ordinance gives its own reason: the authority's makeup and powers are to be revised and the job "returned to a body separate from the Town Council." Ordinance 2026.04 would hand that job to a new Water and Sewer Commission of seven residents and two alternates, appointed to staggered three-year terms instead of the five in the first draft. The council would keep approval over the commission's biggest decisions.

On Tuesday it raised the bar for what counts as big. The draft Town Manager David Cox brought back from a Sept. 29 workshop required council approval for professional services contracts over $25,000 and for capital projects and major contracts over $50,000. Council member Richard Knotek proposed higher figures, and the council went through them one by one.

The limits now in the draft

  • Engineering, legal, financial and other professional services: above $50,000. Knotek had proposed $75,000.
  • Capital projects: above $100,000, and only for projects not already in the approved capital plan.
  • Major contracts: above $75,000, and only when a contract also runs for years (the draft proposes more than three), creates a significant continuing financial obligation for the town and materially affects the system's long-term operation or finances. All four tests must be met.
  • Borrowing: council approval only when the town guarantees it; otherwise the commission could borrow on its own. Cox said he and Director of Finance Jeffery Jylkka would work out the wording.
  • Legal settlements: still above $25,000, which a member said is the town's insurance deductible.
  • The draft sewer rules: who would decide what
  • Council wants a veto over the new sewer board

Knotek said sewer costs reach those figures quickly, that ordinances like this one can go five, 10 or 15 years without review, and that low limits would keep sending the commission back to a council whose members are not experts. The town wants engineers and financial people to volunteer, he said, and the limits would tie their hands. "I think it's a bit insulting to be quite honest," he said.

He asked Cox whether the authority had ever been a problem financially. Cox said it had not: "the organization has done fine financially." The bigger question, he said, was the council understanding in more detail what goes on there.

A member said the $50,000 project limit had been Council member Ted Hintz Jr.'s suggestion, meant to keep the commission from buying land without the council's knowledge. Others said land falls under a different section, which requires a town meeting vote only when town money is used. Members agreed that, as drafted, the commission could buy land with the sewer utility's own money without the council's or a town meeting's approval, the sticking point in September. The draft would still require the commission to tell the council in writing before acquiring significant property, and it counts land bought for a capital project toward that project's cost.

Who the commission works for

Knotek also asked for a sentence near the top of the ordinance saying the commission's primary duty, within its authority, "is to operate in the best interests of the users it serves." Most residents reading the draft, he said, would assume the authority works for the council. "The revenue of the WPCA belongs to the users," he said. Cox is to find the right place for the sentence.

Members also struck "reject and" from the lines letting the council "reject and return" the commission's budget and five-year capital plan. One member said that under state law the council, like the Board of Finance, can make recommendations, but the authority approves its own budget; another said the words gave "a false sense of authority." The council would return the budget with comments.

The commission would report to the council twice a year instead of every quarter, and its chair and the public utilities administrator "may be asked" to appear before the council instead of being required to.

What stays

In appointing members the council "should consider" experience in fields such as finance, engineering and utilities; a resident had asked for "must." The commission would have to notify the council in writing before acting on major matters, including a material change in sewer rates, and the draft says that notice should come at least 25 business days ahead. Any deal over treatment, capacity or shared equipment with another town or regional body would need council approval at any price, including deals with Colchester over the treatment plant the two towns share through the Colchester-East Hampton Joint Facilities.

The council first voted by voice to send the amended draft to a hearing at its next meeting, Nov. 10. After a member asked how much was already on that agenda, it reconsidered and moved the hearing to Nov. 24, the Tuesday before Thanksgiving.

Next ❦ Public hearing at the Town Council meeting: Tuesday, Nov. 24, 6:30 p.m., Town Hall Council Chambers. Cox said a revised draft with the Oct. 27 changes will be at the town clerk's office once the hearing notice is published. The council can adopt the ordinance after the hearing, and would then appoint the commission.
Town Council, Oct. 27, 2026. Watch · Read the Oct. 22 draft ordinance (agenda packet, item 7a)

No answer yet on a water system for 30 Long Crossing

The town takes over a system serving more than 25 customers; members said it likely wouldn't take a smaller one.

East Hampton has received a state form asking it to confirm it would take over a water system proposed at 30 Long Crossing Road, Town Manager David Cox told the Water Pollution Control Authority Oct. 6. Members noted the property is a seven-lot commercial subdivision and the proposal has not gone through land-use approval. The authority took no action.

Under town code and state law, a system serving more than 25 customers comes to the town, Cox said. Members agreed the town would keep its water service area and take over the system if it becomes a community water system; if it doesn't, the town likely wouldn't. Resident Leonard Johnson said the area already has water-supply problems and asked who would pay if a new system fails.

Water Pollution Control Authority, Oct. 6, 2026. Watch

East Hampton Draft Sewer Rules: Commission Would Set Rates

As drafted, the new commission would set your sewer rate. The council would be told, not asked.

East Hampton's draft sewer ordinance would make a new seven-member commission, appointed by the Town Council, the town's sewer authority. The council holds that job for now. It is a working draft: its dollar limits are blank, and the town attorney is reviewing it.

Your rate. The draft leaves sewer connection and use charges, the rates on your bill, with the commission, because state law gives them to the sewer authority. State law also requires a public hearing, announced at least 10 days ahead, before any rate change. The commission would have to notify the council before a "material" rate change, a word the draft does not define. Town Manager David Cox said Sept. 29 the town attorney thinks council involvement in rates is probably fine, so this could still change.

Also the commission's call. Individual requests to connect, assessments on individual properties, orders requiring a property to connect, and technical rules for using the system.

Council approval first. Building projects above a dollar limit; buying, selling or leasing land; large or long contracts; deals with other towns, including Colchester, which shares the treatment plant; borrowing; unbudgeted spending from reserves above a limit; changes to the town's sewer plan, the map of where sewers go and where they are to be avoided; selling the claims the town holds against properties for unpaid sewer charges; settlements above a limit; selling off major parts of the system; and privatizing it or expanding the service area.

Emergencies. The commission, the town's public utilities administrator or the town manager could act without waiting, then report to the council.

Removal. The council could remove a commissioner for cause after a hearing.

As drafted, elected officials would approve the money, land and big contracts, and appointed ones would set the rate you pay.
Next ❦ At a Sept. 29 workshop members leaned toward requiring approval of consulting contracts over $25,000 and other major contracts over $50,000 (more); the land clause is in question. The town attorney reviews the revised draft. No date set for a public hearing on the ordinance.
Draft amendments to Chapter 146 and state statutes, Town Council special meeting/workshop agenda packet, Sept. 29, 2026. Read the draft

Council eyes $25,000 and $50,000 limits for new sewer board

Nothing is final. On the budget, the council would comment, not vote.

The Town Council, which sits as East Hampton's sewer authority for now, went through a draft ordinance Sept. 29 that would hand that job to a new seven-member commission the council appoints. The authority sets sewer rates and plans the system. The draft left its dollar limits blank, and members began filling them in, informally and without a vote.

On spending, members leaned toward requiring council approval of consulting and other professional services contracts over $25,000, and of other major contracts over $50,000. A separate limit for construction projects, also discussed at $50,000, is not settled.

On the budget, Town Manager David Cox said the town attorney thinks council approval is probably fine, but Cox asked whether approval would reach into day-to-day operations and floated review and comment instead. If the commission ignored the council's comments, Cox said, "what happens? I don't know." A member answered, "Kind of like we'll see in three years." Members leaned toward review and comment.

Members also leaned toward three-year terms, staggered, instead of the draft's five. Cox said shorter terms were the town attorney's suggestion; with them, he said, the council could review members more often and decline to reappoint one who is "just not cutting the mustard." The question of land purchases remains open.

The limits would decide which sewer spending comes before elected officials.
Next ❦ Cox will check whether the construction limit is too low, and the town attorney reviews the revised draft. No date set for a public hearing.
Town Council special meeting/workshop, Sept. 29, 2026. Read the draft

Sewer bills are due Oct. 1

They go in the mail Sept. 29

Sewer use bills go in the mail Tuesday, Sept. 29, and are due Thursday, Oct. 1. They become delinquent after Monday, Nov. 2.

The bill can be paid in two equal halves. The second half is due April 1, 2027, and there will be no second bill for it: the stub comes with the October bill.

Keep the October bill. The April payment stub is attached to it.
Next ❦ Payment delinquent after Monday, Nov. 2.
Town Manager's report, Sept. 21, 2026. Read the report

East Hampton wants Joint Facilities to maintain its sewers

Colchester members have raised having each town do its own.

The Water Pollution Control Authority on Oct. 6 voted to tell East Hampton's representatives on the Joint Facilities committee that the town wants Joint Facilities crews to keep maintaining its sewer collection system. No opposition was heard. Members said changing that had been raised by Colchester members.

The interim public utilities administrator said each town pays about $150,000 a year toward that crew and said he didn't think each town could hire the two or three people the work takes. He said Joint Facilities now has about five operators, down from seven in the past: "we're short-handed right now."

Next ❦ The plant superintendent's job is open. Town Manager David Cox said a contract-operations firm is to quote on short-term superintendent help.
Water Pollution Control Authority, Oct. 6, 2026. Watch

Residents push for experience on the new sewer board

Council members who spoke did not take up the change.

The seven-member commission East Hampton's council is drafting would set sewer rates and plan the system. At a Sept. 29 workshop, two residents asked that its members be experienced. One said they "cannot be trained as they go. This is far too important." The other asked that the draft's line saying the council "may consider" professional experience when appointing members say "must."

Council members who spoke did not take it up. "I don't see how we can force a volunteer to have that," one said. Another said it would be surprising to fill seven seats with people "who have all had experience." Town Manager David Cox pointed out that "must" would only require the council to consider experience: "It just says you must consider it." A third member suggested "should."

The resident who asked for "must" also wanted a firm notice deadline, at least 15 calendar days or 10 work days, before the commission acts on a major decision. The draft says "sufficiently in advance." Members did not settle it.

The wording decides whether the council has to weigh experience when it picks the people who would set sewer rates.
Next ❦ The town attorney reviews the revised draft. No date set for a public hearing.
Town Council special meeting/workshop, Sept. 29, 2026. Read the draft

Council wants a veto over the new sewer board

On land purchases, the town attorney's March advice points the other way.

East Hampton's draft rewrite of its sewer ordinance would hand the sewer authority to a new seven-member commission appointed by the Town Council, and would keep the council's approval over the commission's major decisions, including any land it buys. The council, which sits as the sewer authority for now, went through the draft at a Sept. 29 special meeting.

Land is where it stuck. Every member who spoke, "with possibly one exception," wants that approval, Town Manager David Cox said. But in March the town attorney advised that the sewer authority and the Colchester-East Hampton Joint Facilities, which runs the treatment plant the two towns share, hold the legal power to buy land for sewer use, not the council or a town meeting. On that advice the council canceled a planned town meeting vote on buying 292 West High Street for a plant expansion. Public comment on the purchase was in strong opposition, the minutes say.

Cox said the attorney's view turns on who pays: it applies when the utility's own money, from customers' bills rather than taxes, covers the whole cost. Cox will ask him again. One member said limiting what the authority buys with its own money is likely not legal without an opinion saying otherwise. No vote was taken.

If the clause survives legal review, the next sewer land purchase would need the council's approval.
Next ❦ No date set for a revised draft or a public hearing.
Town Council special meeting/workshop, Sept. 29, 2026. Read the draft. Town Council minutes, March 10, 2026. Read the minutes

Why the Town Council is your sewer board

And why that may change

The Water Pollution Control Authority sets sewer rates and plans the system. Right now the seven council members are the authority, an arrangement one member described on Sept. 1 as "hopefully only intended to last maybe six months. We're past that."

On Sept. 8 the council began discussing a revised ordinance: the council would keep acting as the authority on major decisions, and a separate Water and Sewer Commission would handle day-to-day operations. Members noted that legal counsel would need to review it.

Update, Sept. 30: The draft ordinance the council reviewed on Sept. 29 goes a different way. A new seven-member commission appointed by the council would be the sewer authority, and the council would keep approval over its major decisions. Read the latest.

It decides who runs the sewer system day to day.
Next ❦ No date set; the council expects more discussion before an ordinance is drafted.
Town Council minutes, Sept. 8, 2026. Read the minutes